11 kW Rooftop Solar PV Design for a University Engineering Department
Karachi, Pakistan· 2021
HelioScope design of a 10.8 kWdc system for NED University's Mechanical Department: 17.65 MWh a year against a 12.77 MWh load, PR 82.8%.
Challenge
Rooms 72 to 79 of NED University's Mechanical Engineering Department faced chronic energy shortages, with an annual consumption of 12.77 MWh. Fluxiss carried out this work as engineering subcontractor.
Approach
A load analysis gave 35.49 kWh per day. String calculations set two strings of 10 Yingli 540 W modules on a 12 kW Delta inverter, and the system was modelled in HelioScope with a cost analysis.
Result
Annual production was 17.65 MWh at a performance ratio of 82.8%, for an estimated cost of about PKR 855,460 and a lifetime offset of 100 tons of CO2.
Scope of Work
- Load analysis
- String sizing
- HelioScope system model
- Cost analysis
Deliverables
- HelioScope report
- String calculations
- Cost analysis
Similar projects

Hospital Pipe Stress and Acoustic Analysis for Plantrooms and Floor Pipework
Stress and acoustic analysis of mechanical and domestic piping at Midland Metropolitan University Hospital to reduce noise in a hospital setting.

Cooling and Heating Load Analysis for a University Building with a Glass Dome
Space-by-space Carrier HAP loads for 14 zones at SIUE, including an equivalent-volume glass dome model: 180,179 Btu/hr cooling, 8,500 CFM.

1.3 GWac Utility-Scale Solar PV Plant Design in Colorado
RatedPower design of Inovateus Solar's 1.33 GWac Kendall Ranch: 151 power stations, 40,678 trackers, 3.41 TWh in year 1 and PR 87.03%.
Let's Build Something Great Together.
Partner with Fluxiss for engineering that holds up - under pressure, under load, under scrutiny.