Primavera P6 Schedule for an 8.26 MW Factory Rooftop Solar PV Project

Primavera P6 Schedule for an 8.26 MW Factory Rooftop Solar PV Project

Project Lead
Syed Nasir
Lead Consultant, Founder & CEO, Fluxiss
Discipline Lead
Mr. Ahsan
Renewable Energies Lead, Fluxiss
Discuss a similar project

Activity-level Primavera P6 schedule for Gul Ahmed DCM Factory 01's 8.26 MW rooftop solar, tracking 42.94% progress against a 35.22% baseline.

Challenge

The 8.26 MW rooftop solar project at Gul Ahmed DCM Factory 01 needed a schedule that tracked actual progress against baseline across contract, procurement, engineering and execution. Fluxiss carried out this work as engineering subcontractor.

Approach

Fluxiss built the Primavera P6 schedule with a full activity hierarchy, baseline durations, actual dates and percentage completion against BL1, covering imported and local procurement, engineering submittals and installation.

Result

At the update the project was 42.94% complete against a 35.22% BL1 target, ahead of baseline, with a forecast finish of 20 May 2025.

Scope of Work

  • Activity-level WBS
  • Baseline comparison
  • Procurement and execution tracking

Deliverables

  • Primavera P6 schedule and progress update

Codes & Tools

Primavera P6
Our Renewable Energies service
Ready to Start Your Project?

Let's Build Something Great Together.

Partner with Fluxiss for engineering that holds up - under pressure, under load, under scrutiny.