Primavera P6 Schedule for an 8.26 MW Factory Rooftop Solar PV Project
Activity-level Primavera P6 schedule for Gul Ahmed DCM Factory 01's 8.26 MW rooftop solar, tracking 42.94% progress against a 35.22% baseline.
Challenge
The 8.26 MW rooftop solar project at Gul Ahmed DCM Factory 01 needed a schedule that tracked actual progress against baseline across contract, procurement, engineering and execution. Fluxiss carried out this work as engineering subcontractor.
Approach
Fluxiss built the Primavera P6 schedule with a full activity hierarchy, baseline durations, actual dates and percentage completion against BL1, covering imported and local procurement, engineering submittals and installation.
Result
At the update the project was 42.94% complete against a 35.22% BL1 target, ahead of baseline, with a forecast finish of 20 May 2025.
Scope of Work
- Activity-level WBS
- Baseline comparison
- Procurement and execution tracking
Deliverables
- Primavera P6 schedule and progress update
Similar projects

1.3 GWac Utility-Scale Solar PV Plant Design in Colorado
RatedPower design of Inovateus Solar's 1.33 GWac Kendall Ranch: 151 power stations, 40,678 trackers, 3.41 TWh in year 1 and PR 87.03%.

41.6 GWh Commercial Solar Plant Energy Yield Simulation in PVSyst
PVSyst v7.4.8 simulation for the TCP Godowns solar plant: 41.6 GWh a year to grid, P50 1,724 kWh/kWp and PR 82.29%.

296 kW Elevated Commercial Rooftop Solar PV Design
PVSyst-simulated 296 kW elevated rooftop system with 501 × 590 W modules on chemically anchored steel structure, plus layout and wiring drawings.
Let's Build Something Great Together.
Partner with Fluxiss for engineering that holds up - under pressure, under load, under scrutiny.